Friday, October 30, 2020

ESA lays out roadmap to Ariane 6 and Vega-C flights

Vega-C and Ariane 6 are being developed by ESA to assure Europe's independent access to space. The maiden flight for Vega-C is planned to take place in June 2021, that for Ariane 6 for the second quarter of 2022. Solid progress is being made on both Vega-C and Ariane 6 development programmes. Since March, some technical events and the COVID-19 pandemic have both impacted the progress of activities. Uncertainty from COVID-19 still persists globally to date. Vega-C is a more powerful and versatile version of the Vega launch vehicle currently operating at Europe's Spaceport in French Guiana. Vega-C's maiden flight is planned for June 2021. Vega was on track for its return to flight, after the July 2019 failure, with its mission (VV16) in March 2020, but Europe's Spaceport had to be closed due to COVID-19 safety measures. The VV16 launch campaign resumed in May but several further launch attempts were halted due to unfavourable weather. Vega's return to flight, with the new SSMS dispenser carrying 53 satellites, was successfully launched on 2 September. Between February and September no activities for the preparation of Vega-C were possible in the Vega mobile gantry while it housed the P80 solid rocket motor in readiness for flight VV16, due to safety constraints. The qualification at system and subsystems level is currently under finalisation. As from October, all the new solid motors for Vega-C have completed qualification testing. The Zefiro-40 solid rocket motor for Vega-C completed qualification tests in 2019. The final test of the P120C took place successfully on 7 October.


Two Vega flights, VV17 and VV18, are planned before Vega-C. Activities for the modification of the mobile gantry for Vega-C, such as modifications of the fluids networks as well as connection and installation of the new control bench for Vega-C, will have to start after VV18 now planned early February.

Vega-C maiden flight is planned for June 2021.

Vega-C is a project managed and funded by the European Space Agency. Avio is the industrial prime contractor. Arianespace commercialises Vega-C.

Ariane 6
ESA, CNES and ArianeGroup have jointly established a consolidated reference planning for Ariane 6 development and are working as an integrated team in their respective roles to make it happen. This schedule is based on analysis of recent achievements, remaining critical milestones and the impact on the programme caused by the COVID-19 pandemic.

With the successful third static fire test of the P120C solid rocket motor on 7 October, all the propulsion elements of the launcher system have completed their qualification tests.

At Europe's Spaceport, activities for the finalisation of the Ariane 6 launch base are progressing. First integration testing with fullscale 'mock-ups' of the P120C strap-on booster and of Ariane 6's central core took place in the new mobile gantry. Testing of the cryogenic arms that link the launch pad and the launch vehicle are also ongoing at Fos-sur-Mer in France, before shipping to French Guiana.

ArianeGroup is completing the challenging development and qualification of the Ariane 6 Auxiliary Power Unit for the upper stage. This device will allow Europe to offer additional capabilities in satellite deployment for the satellite constellation market.

The first Ariane 6 upper stage has been assembled in Bremen, Germany. Coupling the launcher's tanks with the equipped engine bay of the re-ignitable Vinci engine for the first time. The upper stage is currently undergoing mechanical, fluid and electrical tests, before leaving for further tests at the DLR German Aerospace Center's Lampoldshausen facilities in Germany.

There, the complete stage will be hot fire tested on a new test bench specially developed by DLR for the Ariane 6 upper stage. The Ariane 6 upper stage static fire tests are planned to start in the second quarter of 2021.

In parallel, the first Ariane 6 core stage and the second Ariane 6 upper stage are under preparation. These specimen will be shipped to Europe's Spaceport from Les Mureaux (France) and Bremen (Germany) respectively, for the combined tests campaign.

In the third quarter of 2021, the Ariane 6 launch base will be handed over from CNES to ESA. At this point the Ariane 6 combined tests campaign can start. These series of tests will bring the launch vehicle and launch base together for the first time for integrated tests of multiple systems. This will include a static fire test of Ariane 6 while standing on the launch pad for the first time.

Following the successful combined test campaign and Ground qualification review of the launch system, the first launch campaign, with the integration of the maiden flight hardware, will start.

When all these steps are successfully completed Ariane 6 will be in a position to perform its maiden flight in the second quarter of 2022.

Ariane 6 is a project managed and funded by the European Space Agency. ArianeGroup is design authority and industrial prime contractor for the launcher system. The French space agency CNES is prime contractor for the development of the Ariane 6 launch base at Europe's Spaceport in French Guiana. Arianespace commercialises Ariane 6.

Impact of COVID-19
The measures taken to control the pandemic have seriously impacted the progress of activities both in Europe and at Europe's Spaceport since March 2020, including as a result of social distancing, site lockdowns and reduced capacity at facilities, travel restrictions, quarantines and confinement measures.

This has considerably slowed all working and operational processes for prime contractors and their respective subcontractors around 13 European countries. Ongoing pandemic effects continue to disrupt on-going development and operations.

"We constantly and closely monitor the COVID-19 impact and technical challenges on our ongoing space transportation developments and operations. Together with our contractual partners and participating States, ESA continues to pull together towards our common priority goals which are the maiden flights of Vega-C and Ariane 6," commented Daniel Neuenschwander, Director of Space Transportation at ESA.

Tuesday, July 10, 2018

Largest-ever solid rocket motor poised for first hot firing

This week, the largest solid rocket motor ever built in one piece will be test fired at Europe's Spaceport in French Guiana for the first time. This important milestone validates the booster for use on Vega-C next year and on Ariane 6 from 2020. Fully loaded with solid fuel, the P120C rocket motor common to Europe's future launchers Vega-C and Ariane 6, will be held vertically in the test stand and ignited. Sensors will gather about 600 measures during the test. The P120C is 13.5 m long and 3.4 m in diameter, contains 142 tonnes of solid propellant and provides a maximum thrust of 4615 kN (in vacuum) over a burn time of about 135 s. The design builds on existing expertise and lessons learned with Vega's P80 first stage motor. P120C will replace P80 as the first stage motor of Vega-C. Two or four P120Cs will be strapped onto Ariane 6 as boosters for liftoff. All main components of the motor such as nozzle, igniter, solid propellant, and insulated motor case have already been tested separately. This static firing will prove these technologies, materials and production techniques in combination and validate the behaviour of the assembled motor.


The test stand with the tools and equipment that will secure the P120C for its test firing, have had to be modified or developed to accommodate this huge motor.

Recently a full-scale model of the P120C filled with inert propellant allowed engineers to verify tools, check connections and perfect procedures.

Information gathered during this static firing will allow engineers to compare their numerical models against observed reality to consolidate the P120C design.

This will guide the design of the P120C qualification motor that will be static fired at the end of the year.